The MKT Bridge has reopened

This pleasant surprise came out on Thursday evening.

A vital and long-unused bridge in a buzzing Houston neighborhood is set to reopen.

The M-K-T Bridge, located in The Heights near White Oak Bayou, will be accessible to users on Friday, May 27, the Houston Parks Board announced. A key artery for walkers and joggers, the bridge spans over the bayou at I-10 near Studemont Street. Out of use since it was significantly damaged by a fire in August 2020, the bridge reopens after repairs began in March.

This reopening is actually ahead of schedule, as the bridge was set to open this summer, as CultureMap previously reported. It provides a pivotal outlet for those who use the M-K-T Trail, which connects The Heights to Sawyer Yards and the Washington Avenue Corridor area.

See here for the background, and here for the Houston Parks Board’s announcement. As you know, I’ve been following the White Oak Bike Trail extension construction, which connects up on the west side of the bridge. I have not seen any construction activity myself, but either I haven’t known where to look or it’s been happening when I haven’t been looking. In any event, the bridge is now open, and here’s the press release I got about it on Friday:

Houston Parks Board is excited to announce MKT Bridge is now open to the public!

An essential component of the trail system in the Heights connecting to White Oak Bayou Greenway, MKT Bridge has been fully restored just in time for summer. Working closely with the City of Houston, owner of the bridge, and Harris County Flood Control District, Houston Parks Board worked diligently to repair the bridge after it sustained extensive damage due to a fire in August 2020.

Initial repairs to MKT Bridge began in summer 2021. While conducting this repair work in August 2021, contractors and structural engineers found additional damage caused by the fire that was not visible during the initial assessment of the bridge’s condition. It was determined further repairs were needed before the bridge could safely reopen, which was disappointing to the community users.

Following expedited approval of the additional design plans from the City of Houston and Harris County Flood Control District, on site construction to MKT Bridge resumed in March 2022.

The recently completed repair work included adding steel channels and bracing to the timber piling, transferring weight from the bridge to the ground.

Houston Parks Board is thrilled to have this essential connector reopen in time for summer. Thank you for your understanding as we worked as quickly as possible to make MKT Bridge safely accessible once again, and to the City of Houston and Harris County Flood Control District for the partnership in this effort.

That’s from the email, which also has a link to a bunch of photos, from the ribbon-cutting event and from the construction, which I find fascinating because I just never saw any of it while it was happening. Just goes to show me, I guess. I can’t wait to give it a go myself. I’ve also got some more pix from the bike trail construction that I’ll run shortly. For now, hooray! The MKT Bridge is back, and many bicyclists in the area will be delighted. The Leader News, Community Impact, and the Chron have more.

Related Posts:

This entry was posted in Planes, Trains, and Automobiles and tagged , , , , , , , , , , , . Bookmark the permalink.

2 Responses to The MKT Bridge has reopened

  1. Jason Hochman says:

    Yes, they sent me an email about this. I was shocked. But great to hear this news. I think that you may not have seen the construction because it was under the span of the bridge.

  2. Pingback: I don’t really know what the White Oak Bike Trail extension is going to look like – Off the Kuff

Comments are closed.