Metro still dealing with CAF problems

The more things change

HoustonMetro

Metro and the maker of its newest light rail cars have had many costly and time-consuming conflicts. The latest is forcing the transit agency to spend $1 million so its mechanics can lift the vehicles.

The $153 million contract with CAF U.S.A., the American wing of a Spanish firm, has been problematic for the Metropolitan Transit Authority during its expansion of Houston’s light rail network. The company ran into problems complying with requirements for American-made products in 2010. Then in late 2013, Metro and CAF engaged in a dispute over timely delivery of the 39 light rail cars included in the contract, the last of which still has not been delivered to Houston.

Now transit officials and the rail-car builder disagree on who is responsible for a design deviation that prevents Metro’s lifts – which raise the train for mechanical work, much like a lift in an auto mechanic’s garage – from raising CAF’s cars.

“To be blunt, the question is, is it a breach of contract,” Metro CEO Tom Lambert said.

CAF officials did not respond to requests for comment on Tuesday.

To do routine maintenance on the vehicles and get the work completed, Metro will pay to retrofit its lifts so they can hoist the CAF cars. Lambert said Metro will seek to recover some or all of the $1 million from CAF.

[…]

Metro officials have said for more than a year they are confident in the quality of the rail cars. But the procurement process has been chaotic, they say.

Lambert said Metro will hold CAF responsible where practical, while acknowledging the contract has been troublesome.

“There are a lot of lessons learned in this process that will be valuable moving forward,” Lambert said. “We know, and I think there is an acknowledgement from CAF now, that you can’t build a rail car in 24 months. But that’s what they said they could do.”

As you may recall, the original issue with CAF had to do with them not complying with federal law on building the rail cars entirely in the US. That issue was settled in 2010, with CAF building new facilities here in the US to handle construction. That ultimately led to delays in delivery, which was one reason why the new rail lines didn’t open till May, months after the original due date. Let’s just say that I hope we have indeed learned from this process, and that I hope the matter in question can be settled quickly.

From the “Always Look On The Bright Side Of Life” department

Every dark cloud has a silver lining, y’all. You just have to know where to look for it.

Metro’s four-month delay in opening two rail lines will give the agency time to obtain enough cars to prevent severe crowding when trains start rolling.

Fourteen of 39 new rail cars that the Metropolitan Transit Authority ordered in 2012 will be ready to carry riders by April 1, Metro CEO Tom Lambert said Thursday. An additional 19 cars will still be in testing.

“We are making very good headway,” Lambert said.

The Green Line, east of downtown along Harrisburg, and the Purple Line connecting southeast neighborhoods to the central business district, are scheduled to open April 4. By that time, with Metro’s 37 existing cars and 14 new ones, Metro officials said they can run constant service, though perhaps not as frequently as envisioned.

[…]

When the new lines open, Metro spokesman Jerome Gray said, the expected number of cars will allow for two-car sets along the Red Line every six minutes during peak periods – around 5 a.m. to 8 p.m. daily – and single trains every 12 minutes along the Green and Purple lines.

See here, here, and here for the background. I don’t really have anything to add to that, so I’ll leave you with this.

Remember, if life seems jolly rotten, there’s something you’ve forgotten.

We’ll get our new trains in January

We have a deadline.

The company building Metro’s new trains will deliver the final car to Houston five months late, according to a revised schedule submitted to the transit agency.

The Metropolitan Transit Authority is reviewing the schedule, spokesman Jerome Gray said, and hasn’t agreed to the new timeline. The revision was one of the  promises the rail car builder, CAF U.S.A., made when the company acknowledged substantial delays in production in January. Rather than deliver the last batch of 39 train cars in August, the company now expects to deliver the last train in January.

Production problems with the first railcar, sitting at Metro’s south Houston rail maintenance facility, led to substantial delays in production. Workers at CAF’s facility in Elmira, N.Y., are building the second car now, with a fix to a troublesome water leak that led to the problems on the first car. Once the second train passes its tests, and the fix is verified, production will accelerate.

To catch up and deal with other production issues, CAF is expanding its plant, but it still will not meet the contractual deadline to deliver the trains. Under the deal signed in 2011, Metro should already have 16 trains in Houston ready to test and start service. The new train cars are critical to starting service on the East and Southeast lines, set to open later this year.

Without the trains, Metro plans to start limited service on the two new lines by taking trains off the Red Line. Reducing  double-car trains to single cars on the Red Line will lead to severe crowding, officials and riders said.

Based on the revised schedule, Metro would have 21 rail cars by the end of September, when service on the lines could begin. Not all of those trains can immediately enter service, however, as they will need testing and final assembly in Houston.

See here and here for the background. That’s longer than I’d have liked for this to take, but at least there’s a target date. Other than having to temper our expectations for the ridership numbers in the first few months of service, and continuing to be prepared to sue if necessary, I don’t know that there’s anything else to be done but wait and hope this time they mean it.

Riding that crowded train

Metro ponders its options for dealing with potential delays in the delivery of new railcars.

Metro officials said Wednesday that the best solution to an expected shortage of railcars might be to limit trains on the main light rail line to one car rather than two, freeing up cars from the current fleet to serve new lines scheduled to open in September.

Currently, Metro tethers two cars together most of the time on the decade-old Main Street line to ensure sufficient capacity.

Officials acknowledged that the decision would frustrate riders, likely leading some to abandon using the line.

“If you try to use our current fleet to run East and Southeast,” said board member Christof Spieler, referring to the new lines set to open this year, “that means leaving passengers behind.”

Officials are waiting for 39 new railcars from the manufacturer, CAF U.S.A., but they still don’t know exactly when the cars will arrive. At least two are likely to be in service by September, Metro officials said.

The company is months behind a schedule that calls for it deliver the final car by September, and it has yet to deliver a viable vehicle. The first car to arrive in Houston came in December – five months late – and still hasn’t passed a key leak test. The train also exceeds weight specifications, meaning it will cost more to operate.

Metro’s board met Wednesday to examine options for operating the new East and Southeast lines and the existing Red Line with the agency’s 37-train fleet. Both new lines are on pace to open in September, said David Couch, vice president of rail construction for Metro.

To have trains arrive every 12 minutes on the two new lines, and assuming no CAF cars arrive by opening day, Metro will have to pull 10 trains from the current route.

See here for the background. Assuming that the two that Metro thinks are likely to show up on time do so, then eight cars will need to be diverted. If “at least two” turns out to mean “more than two”, so much the better. On the other hand, any unexpected maintenance will be that much more disruptive. I don’t see how Metro has much choice for how to deal with this in the short term, so it’s really just a question of how short the short term is. A month, maybe two months, to get enough cars in so that the Main Street line doesn’t need to be cannibalized any more, that’s probably not a big deal. Longer than that, especially if the deadlines are fuzzy and promises get broken along the way, that’s a problem. Other than be prepared to sue for damages if it comes to that, I don’t know what else Metro can do about it right now.

I got those “can’t get my rail cars built on time” blues

Actually, I don’t, but Metro does.

The company building 39 new Metro railcars has yet to deliver an acceptable vehicle almost six months after the original due date, potentially delaying full service for rail lines scheduled to open later this year.

The first car hasn’t passed a required water leak test and exceeds the maximum weight specified in the builder’s contract with the Metropolitan Transit Authority. In a Dec. 30 letter to CAF USA, the American subsidiary of the Spanish train-building giant, interim Metro CEO Tom Lambert demanded that the company explain how it will deliver all the cars by the Sept. 25 deadline.

“It is imperative that CAF demonstrate to Metro that it is seriously willing and able to meet its obligations,” Lambert wrote. Metro is withholding a $12.8 million payment until an acceptable rail car is delivered, he wrote.

In a reply, CAF’s worldwide CEO, Jose Maria Baztarrica, assured Lambert that U.S. representatives of the company would come to Houston to “fix all the various issues.”

Continued delay would leave Metro officials with options for opening the lines on time, but possibly not on a full schedule. Fewer railcars ready to hit the street could mean that trains operated less frequently or failed to cover the entire route.

“We can work through it, and we will,” Metro board chairman Gilbert Garcia said, stressing the important factor is that CAF deliver high-quality vehicles. “We have to be prepared that the cars are delayed and now we need to have a plan going forward of what we’re going to do.”

The railcar manufacturer is now promising swift action to get this resolved.

“If they are having a problem, then to me it is a big problem, even if it is a minor fix,” said Andres Arizkorreta, CEO of Construcciones y Auxiliar de Ferrocarriles, commonly known as CAF. “These are things we must do.”

[…]

Arizkorreta flew to Houston on Wednesday. On Thursday morning, he assured Metro officials the water leak would be fixed within 10 days by installing a gasket

Remedying the leak, which was minor, is necessary before the car can enter service by undergoing weeks of on-track testing, interim Metro CEO Tom Lambert said.

“The best thing we can do now is get this one at the test track,” Lambert said. “The sooner we do that, the sooner we can build the others.”

Additional cars might come at a brisker pace. Manufacture of the cars will accelerate as CAF U.S.A. expands its Elmira, N.Y., plant, Arizkorreta assured Metro.

Officials said they were pleased with the quick corrections.

“I am convinced this is moving in the right direction,” Metro chairman Gilbert Garcia said.

About 100 workers will be hired specifically to handle Houston railcar building, roughly doubling the staff now handling the order. CAF agreed in writing Thursday to give Metro a revised delivery schedule by Feb. 15.

That all sounds good, but the weight issue remains a problem. It’s not clear how that will be fixed. I’m going to be optimistic and say that this will mostly get worked out before the Southeast and Harrisburg lines open, but we’ll know more in a month. I hope it doesn’t cause any operational problems, or force reduced frequencies when the new lines open. Metro had already set its schedule back by a year after nearly blowing its Full Funding Grant Agreement due to the shenanigans of previous CEO Frank Wilson, who was trying to circumvent the FTA’s Buy American requirements. It’s possible that in the absence of those requirements, or at least in the absence of Metro trying to get around them and getting caught at it, that we’d be farther along now. Nothing can be done about any of that now, so let’s keep CAF’s feet to the fire and hope they have good news in February.