Time for the annual “Are we ready for a big storm?” story

The answer, of course, is no, not really.

After Tropical Storm Allison’s devastating floods, the Houston area widened its bayous and hardened its infra­structure. After Hurricane Rita’s deadly gridlock, the state revamped storm communications and evacuation plans.

Yet since Hurricane Ike’s enormous surge wiped out coastal communities and its $30 billion in damages dwarfed those of the other two storms, not much has happened.

Which is to say that [Wednesday] — the first day of a new hurricane season that’s expected to be quite active, and nearly three years after the costliest storm in Houston history — the region remains as vulnerable as ever to storm surge.

In Ike’s wake the state formed the Gulf Coast Community Protection and Recovery District, which includes Brazoria, Chambers, Galveston, Harris, Jefferson and Orange counties, to study storm surge remedies and possibly put them into effect.

But so far, the district has no federal or state funding.

State funding? Don’t make me laugh. Rick Perry has actually been using the prospect of a hurricane as a justification for not using more of the Rainy Day fund, even though that’s never been the fund’s intended use. As for federal money, there was probably a brief moment in 2009 when something like that could have been part of the stimulus package – Lord knows, we should have aimed to spend a ton more on infrastructure projects. That moment is long gone, and even if our ridiculous Republican members of Congress wanted to push for this, the only way the rest of the Republican majority would let it happen would be if the Democrats would agree to pay for it by cutting services elsewhere, much as they insisted on doing so for tornado relief. Meanwhile, a bunch of white swans are swimming by, but no one is paying attention to them.

As for what could be done, we’re familiar with the Ike Dike, but there’s another possibility out there.

“An environmental and industrial disaster that will put the Ship Channel down for months is my biggest fear,” [Phil Bedient, a Rice University civil engineer who studies flooding] said.

He said most facilities in the port area are protected from about a 14-foot surge, with some facilities a bit higher. Had Ike come ashore 25 miles down the coast, at the west rather than the east end of Galveston Island, it would have pushed a surge of up to 19 feet up the Ship Channel, Bedient said.

As a result of these concerns, Bedient and colleagues plan to propose putting a large gate at the entrance to the Ship Channel.

Such a gate would cost far less than the so-called “Ike Dike” proposal, and would cause less concern among environmentalists.

As it happens, Prof. Bediant had an op-ed in the Chron on the same day, also sounding the alarm about storm preparedness. Unfortunately, he didn’t go into any detail about the Ship Channel gate. I suspect it’s laid out in detail in this report on Hurricane Ike, which is on the Severe Storm Prediction, Education and Evacuation from Disasters (SSPEED) Center‘s website. Read it and be prepared to take a short quiz on it for next week.

Related Posts:

This entry was posted in Hurricane Katrina and tagged , , , , , , , , , , , , , . Bookmark the permalink.