Uptown update

The work is ending, the work continues.

The end is near for construction that has clogged Post Oak and delayed drivers, but the buses at the center of the project will not start rolling for at least another year as officials grapple with roadblocks threatening to push the final route three years past its original completion date.

Months of additional work lies ahead on the dedicated bus lanes in the middle of the street as crews complete the stations that will connect passengers to the rapid transit line. Though once on target to ferry passengers this holiday season, workers still are installing electrical and fiber optics systems so the buses can operate, as they pour the last segments of concrete along the widened roads from Loop 610 south to Richmond.

As a result the buses, which officials at one point had hoped would ferry visitors for the 2017 Super Bowl, will not carry passengers until 2020.

Even when Metropolitan Transit Authority begins operating the buses along dedicated lanes in the center of the street, riders and operators face months, perhaps years of detours at both ends of the project as two Texas Department of Transportation projects take shape.

“It will operate. It just may not be the guideways we want eventually,” Metro board member Sanjay Ramabhadran said.

[…]

As Post Oak proceeds, TxDOT is building an elevated busway along Loop 610 so the large vehicles will move from their Post Oak lanes to an overpass that takes them directly to the transit center. Construction, estimated to cost $57.2 million, started earlier this year. Completion is set for late summer 2020, meaning a few months of the large buses slogging north to the transit center.

On the southern side of the bus project, another challenge looms. A massive rebuild of the Loop 610 interchange with Interstate 69, already a year into construction, will worsen as the project moves toward its 2023 completion.

Of particular concern is the timing of work south of Richmond, where Post Oak morphs into the southbound Loop 610 frontage road and goes under I-69 before re-emerging at Westpark Drive. Referred to by transportation officials as the “portal” along with the underpass that carries northbound frontage traffic beneath the interchange, it is the critical link for Post Oak buses headed to the new Bellaire transit center.

We were promised that the service would begin in 2019, but between politics and Harvey and whatever else, that’s the way it goes. Solving the problem of extending this to its intended endpoints at Northwest Transit Center and the to-be-built transit center in Bellaire, that’s the big challenge. Among other things, right now this is the main connection to the rest of the city from the Texas Central terminal. This thing is a big deal, and we’re going to need it to be done right.

Related Posts:

This entry was posted in Planes, Trains, and Automobiles and tagged , , , , , , , , , . Bookmark the permalink.

One Response to Uptown update

  1. Jules says:

    The main connection to the rest of the city from the [proposed] Texas Central Terminal? LOL No. That would be cars and freeways.

    The ROD was just delayed until 2020, which somehow Texas Central is spinning into a positive and saying construction will start in 2019. No on 2019 too.

Comments are closed.